Hello DM experts,
Is there a way to transfer rework orders created in S/4HANA without a header material (using transaction CO07) into SAP Digital Manufacturing? If that’s not supported, what is the recommended approach for handling rework orders within SAP DM?
Thank you and best regards, Gizem
Request clarification before answering.
Hi,
i would suggest you to customize the XSLT for LOIPRO05 and check if the IDOC has or not the header material.
In case it is empty/blank you can create a DUMMY material inside SAP DM and attach those orders to the same DUMMY materials.
So with this you will have your rework order inside SAP DM.