on 2020 Mar 17 11:30 PM
I am very new to SAP and have what I think may be a difficult task for a beginner.
I am looking to use the transaction COOIS (or any similar transaction) to get the scheduled start, scheduled finish, actual start, actual finish at each operation for a particular production order. Any tips or guidance would help immensely!
Thanks
Request clarification before answering.
Jacob,
You might want to tag your post with the relevant PP tags.
EAM is more for plant maintenance..
.
PeteA