GANTT CHART IN CPROJECTS- 4.0

Former Member
0 Likes
175

Can we have 3 sets of Dates (Basic Dates, Forecast Dates, Actual Dates) with both Earliest & Latest Dates options in cProjects as we have in R/3 PS ? If this is not possible, can we view both operative version and project version dates simultaneously in the GANTT ? Is it possible to chose different colours for different sets of dates as defined by the user?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member201206
Active Contributor
0 Likes

There is no date set 'Forecast' in the cProject as it in the ERP PS.

In the User-settings in the cProject application you can determine which dates should be showed in the GANTT. A dynamisic swith like ERP PS is not possible.

As far as I remember, there is a note, which describes how to set color in GANTT. If you donot find it, please let me known.

Kind regards,

Zhenbo