on 2018 Aug 01 9:35 PM
I want to create a production order for a material. Fix the basic finish date. Then when MRP runs, it does NOT create exception message for the order. It instead may create new planned orders if needed.
Example: Assume the IPT for the material is 10 days and it is the first day of the month. and the material MTS
I have a production order for 50 pieces with basic finish date of the last day of the month. I also have a demand for the last day of the month for these 50 pieces. (assume zero GR days). Now I get new demand for 50 pieces due 5 days before the end of the month. I want to see a new planned planned order. for the 50 pieces not an exception message on my first order to pull it in and the new planned order after it.