on 2011 Jan 21 8:54 PM
Hi,
When i export a cProject to MSProject get an error MSProject: Security list is invalid.
Can someone help me to resolve this issue. Im using MS Project 2010.
Thanks in advance.
Regards
Request clarification before answering.
Hello Guys,
I see that this is a very old post and it is still open.
Following are the steps that I have done to solve above issue
1. Configure whitelist: T Code = WDR_ACF_WLIST
2. Generate Certificate: T code = WDR_ACF_GEN_CERT
3. Distribute/ Install Certificate on user computer: ACF_WHITELIST_SETUP
In the first step where you add directory for upload and download, make sure you add directory to which user has access to. So in my case, my system was on domain, I had to use administrator login where I found that it is access issue. Then I configured directory which I had access (for example : C:\users\mahk\SAP). I did not get this error thereafter.
Regards
Mahendra Kadam
(reward points if you find this useful)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Luiz Victor Santos
I'm using MS Project 2010 version and got success as export projects. I have problems and errors on import, but the export is OK.
As for the problem you have is related to installation of the security certificate. Have you checked it in the Back-end Transaction WDR_ACF_WLIST?
Dirlei Andrade
PS. PPM. FI-AA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
please read the chapters u201CDefinition of Security Lists for OfficeControlsu201D and
u201CMaking Settings for Microsoft Project Integartionu201D in the Configuration Content,
available as PDF file attached to SAP Note [1411953|https://service.sap.com/sap/support/notes/1411953].
You may also have a look at:
[SAP Note 1502999 |https://service.sap.com/sap/support/notes/1502999]from NW provides some additional information about the
configuration and set-up of whitelists and also on the distribution of
the whitelist certificates on the frontend PCs (required for
import/export from/to MS Project). More details are available in the
online documentation:
[http://help.sap.com/saphelp_nw70ehp2/helpdata/en/ed/29093b519e4f0db9be6063526537f5/frameset.htm|http://help.sap.com/saphelp_nw70ehp2/helpdata/en/ed/29093b519e4f0db9be6063526537f5/frameset.htm]
Kind regards,
Florian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi;
Check out this wiki page --> http://wiki.scn.sap.com/wiki/display/PLM/cProjects+%28PPM%29+integration+with+MS+Projects
Regards,
Mariano
Hello Experts,
Can any one have answer for this problem , I am facing the same , however I need the output in MS Project. Thanks in advance.
regards
Vagesan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
did you check SAP Note 1502999 (especially the part about paths and directories) ?
Kind regards,
Florian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Nobody?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.