Hi
there seems to be an error in https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/d6c1ceb7e0074cd1a8f28dad8a1a649c/9517d652293c0026e10...
They say go to Master Data -> Master Project -> Define Access Control in customizing.
I can not find a folder called "Master Project" within SAP CPM customizing.
Kind Regards
Markus
Request clarification before answering.
In SPRO it might be shown as Commercial Project.
Commercial Project Management -> Master Data -> Commercial Project -> Define Access Control
In CPM the very first config step is to set the term you wish to call the Master Project. Under Define Custom Term there are 7 options for different industries.