Dynamic Plan Delivery Time for Purchase requisition in MRP

Rangaa
Participant
View Entire Topic
Caetano
Product and Topic Expert
Product and Topic Expert

Hello

I don't think you can influence the planned delivery time with variant configuration. 

BAdI MD_MODIFY_SOURCE allows you to use your own logic to determine the planned delivery time.

Regards,
Caetano 

Rangaa
Participant
0 Kudos
Hi Caetano, Thank you for the response. Will it get triggered during the MRP run ? I have use other exits but those are getting triggered in ME51N and not during the MRP. i dont want PR to get Firm if i implement the custom logic
Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos
Yes, it will get triggered during the MRP run and it does not firm the PR.
Rangaa
Participant
0 Kudos

Hi Caetano,

MD_MODIFY_SOURCE is not getting triggered at MD01N, i have used MD_MRP_PARAMETERS and it satisfies my requirement in MD01. Do we have any BADI which works similar MD_MRP_PARAMETERS in MD01N. I have checked your blog for new BADI PPH_SUPPLY_DEMAND_LIST introduced after 2022 but i am working on 1909. 

Br,