Dynamic Plan Delivery Time for Purchase requisition in MRP

Rangaa
Participant

Accepted Solutions (0)

Answers (3)

Answers (3)

Caetano
Product and Topic Expert
Product and Topic Expert

Hello

I don't think you can influence the planned delivery time with variant configuration. 

BAdI MD_MODIFY_SOURCE allows you to use your own logic to determine the planned delivery time.

Regards,
Caetano 

Rangaa
Participant
0 Kudos
Hi Caetano, Thank you for the response. Will it get triggered during the MRP run ? I have use other exits but those are getting triggered in ME51N and not during the MRP. i dont want PR to get Firm if i implement the custom logic
Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos
Yes, it will get triggered during the MRP run and it does not firm the PR.
Rangaa
Participant
0 Kudos

Hi Caetano,

MD_MODIFY_SOURCE is not getting triggered at MD01N, i have used MD_MRP_PARAMETERS and it satisfies my requirement in MD01. Do we have any BADI which works similar MD_MRP_PARAMETERS in MD01N. I have checked your blog for new BADI PPH_SUPPLY_DEMAND_LIST introduced after 2022 but i am working on 1909. 

Br,

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Hello 

The following note provides a list of the Classic MRP ABAP BAdIs and the equivalent AMDP BAdIs that are called in MRP Live:

2268085 - S4TWL - MRP Live on SAP HANA - MD01N

Regards,
Caetano 

DerekDing
Product and Topic Expert
Product and Topic Expert
0 Kudos

The Planned delivery time is a fixed value in MRP2 View of material master data or in PIR, so if you want to Variant configuration characteristics value to calculate, you should customize a program and logic to change this filed before running MRP.

Material master data:

DerekDing_0-1742269361351.png

PIR:

DerekDing_0-1742271532293.png