on 2025 Mar 17 7:28 PM
Hi Experts,
I have requirement where, I want to use Variant configuration characteristics value to calculate the Planned delivery time in PR.
Best Regards,
Rangaa
Request clarification before answering.
Hello
I don't think you can influence the planned delivery time with variant configuration.
BAdI MD_MODIFY_SOURCE allows you to use your own logic to determine the planned delivery time.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Caetano,
MD_MODIFY_SOURCE is not getting triggered at MD01N, i have used MD_MRP_PARAMETERS and it satisfies my requirement in MD01. Do we have any BADI which works similar MD_MRP_PARAMETERS in MD01N. I have checked your blog for new BADI PPH_SUPPLY_DEMAND_LIST introduced after 2022 but i am working on 1909.
Br,
Hello
Hello
The following note provides a list of the Classic MRP ABAP BAdIs and the equivalent AMDP BAdIs that are called in MRP Live:
2268085 - S4TWL - MRP Live on SAP HANA - MD01N
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The Planned delivery time is a fixed value in MRP2 View of material master data or in PIR, so if you want to Variant configuration characteristics value to calculate, you should customize a program and logic to change this filed before running MRP.
Material master data:
PIR:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.