Hi All
Can you please suggest how to add personal responsible in decision point.
Regards,
Gopi.
Request clarification before answering.
Hi Yaswanth,
I think the way to deal with it is to include the approving users/roles as responsible at each decision point.
The SAP note https://launchpad.support.sap.com/#/notes/2692208 should be taken into account.
Cause
The fields "Responsible Role"/"Responsible Resource" are not valid for the Decision Point of an Item.
Resolution
The fields are not fetching the role/resource from the assigned Project Management Project. As the fields are not relevant for the Decision Point of an Item you can hide them (RESPONSIBLE_NAME, RESPONSIBLE_ROLE) in the field-configuration for the object type EPO.
(Spro > SAP Portfolio and Project Management > Portfolio Management > Global Customizing > Global Field Settings > Define Custom Field Configuration)
The fields "Responsible Role" and "Responsible Resource" are only relevant for the decision point of an initiative. The fields "Responsible Role"/"Responsible Resource" of a Decision Point in an Initiative are fetching the roles/resources from the corresponding initiative.
I hope it helps you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Add them in the Repsonsible Resource in the DP details.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.