cancel
Showing results for 
Search instead for 
Did you mean: 
Read only

cProjects - PS - elements on the first level in reversed order

Former Member
0 Likes
246

Hello,

I am using the hierarchical Accounting with PS and facing a problem with the order of the created elements.

The project definition and the second level are in the correct order. Somehow the first level (-> the level with the phases in cProjects) are in reversed order.

Can someone tell possible reasons for this?

Thx, Max

Accepted Solutions (1)

Accepted Solutions (1)

former_member201206
Active Contributor
0 Likes

Hi Max,

It is a known problem, but there is no solution so far . The purpose of the replication is for the controlling, and from the controlling point of view. It does not care, which wbs is on the left or on the right. There is even a note to indicate this system behaviour.

Kind regards,

Zhenbo

Former Member
0 Likes

Hello Zhenbo,

thx for this answer.

Greetings, Max

SaschaS
Participant
0 Likes

Hello Max,

I agree with Zhenbo's answer. I had the same problems and an equal result.

Cu, Sascha

Answers (0)