Hi All,
I have a question regarding cProjects replication to PS project.
We are creating and cProjects structure and replicating to PS projects.
my question is, is it is possible to replicate cProjects Task,Phase, after release of cProjects?.
I mean to say, we have already relocated cProjects to Ps project by changing status to release-replicate. however we added new Phase/taks to cProjects, will this new phase/task will be automatically replicated to PS projects strcture or how can we do this?
Thanks
Amit
Request clarification before answering.
Dear Amit,
Yes, the new phases/tasks will be replicated to PS-project when saving the Project Management Project.
Best regards,
Judith