on ‎2012 Jul 09 5:59 AM
Hi,
We are facing an error while adding Object link to WBS element (PS) using the link Project Management ----Structure ----object link--
group - WBS element (PS)
Link to - WBS element (PS)
WBS element - No item displayed .
getting error message "Communication error with source system of Object tyepe WBS element (PS) occured.
Appreciate your response to resolve this issue...
we have PPM 5.0 and ehp5
thanks in advance..
matt
Request clarification before answering.
Hi Matt,
check the customizing of the object link, maintain the destination to your ERP system and ensure that this is working in SM59.
Best regards
Thorsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Matt,
if I understand you correctly, you create the object link manually and on the STRUCTURE tab in cPro, not via the accounting tab. Right?
Such object links are not visible in CJ20N. CJ20N will only show the links from cProjects accounting integration (you either create the WBS automatically or link it manually on the accounting tab). But that is a different customizing in cProjects.
Best regards
Thorsten