on 2015 Jun 09 12:51 PM
Hello together,
i know that it is possible to implement a Milestone Tab in cProjects, where you can grafically see all Milestones of the Tasks.
How can I do this?
Thank you!
Request clarification before answering.
Dear Rüya,
the following switch must be activated:
Area: '0002' - Master Switch
Name: '0013' - Milestone Trend Analysis
settings = 'X'
Afterwards, you can activate the milestone trend analysis for relevant project
types in project type Customizing. (See SAP Note 1759150.)
Best regards,
Judith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.