on ‎2007 Aug 14 9:32 PM
Gurus,
I am looking for the attribute which corresponds to the task's 'Percent Complete' field. I intend creating an Evaluation Layout with 'Percent Complete' as one of the columns. Just not able to find out.
Please suggest.
Thanks and Regards.
Request clarification before answering.
Hi Bittu,
The 'work_complete' may fullfill your requirement, which is defined as
sum. actual work / ( sum.rem.work + sum.actual work)
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Zhenbo,
Thanks for responding.
I did try 'Work Complete'. I have a scenario wherein, for a task, the 'Work' is 50 hrs. 'Confirmed' is 25 hrs. 'Remaining Work' is 25 hrs. By this, I should get 50% as the 'Work Complete'. I get 0 in Evaluations.
There's another field 'Percent Complete'. This is what I was looking for. I inentded rolling up the values for each task in a phase to the phase and finnaly to the project. But having not found the 'percent Complete' for the task, I am not able to proceed.
Thanks and Regards.