cancel
Showing results for 
Search instead for 
Did you mean: 
Read only

cProject & Earned Value progress

Former Member
0 Likes
214

Hi,

I've seen the earned value report in Evaluation of cProject, but all values such as BCWS, BCSP, ... are zero.

can anybody share with me documents of calculating earned value in cProject?

Thank you verymuch

longnv@cybersoft-vn.com

Long Nguyen

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member201206
Active Contributor
0 Likes

Hi Long,

cProject does not have it own eared value logic. Actually it uses object link to get the values be displayed. Please check,

1 . if the object link of the involved project is maintained,

2. if the linked object has the BCWS, BCSP values in the backend system.

Kind regards,

Zhenbo

Former Member
0 Likes

HI Zhenbo,

Thank you very much for your reply.

if the object link of the involved project is maintained then Earned value such as BCWS, BCWP, POC in cProject equal to values display in transation CNE5?

Thanks you

Long Nguyen

former_member201206
Active Contributor
0 Likes

Hi Long,

To be honest, I have never tested the functionality with POC value myself.

But the evaluation of cProjects object link is to pull the values from the ERP backend system and display it. The core logic, how to determine such values, is still 'only ' available in the ERP backend system. A similar case is to evaluate the plan, actual costs & budget from the R/3 linked objects. All the information are pulled from the ERP system.

P.S: Which evaluation do you use?

Kind regards,

Zhenbo