on ‎2007 Dec 12 4:36 AM
Hi,
I've seen the earned value report in Evaluation of cProject, but all values such as BCWS, BCSP, ... are zero.
can anybody share with me documents of calculating earned value in cProject?
Thank you verymuch
longnv@cybersoft-vn.com
Long Nguyen
Request clarification before answering.
Hi Long,
cProject does not have it own eared value logic. Actually it uses object link to get the values be displayed. Please check,
1 . if the object link of the involved project is maintained,
2. if the linked object has the BCWS, BCSP values in the backend system.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Long,
To be honest, I have never tested the functionality with POC value myself.
But the evaluation of cProjects object link is to pull the values from the ERP backend system and display it. The core logic, how to determine such values, is still 'only ' available in the ERP backend system. A similar case is to evaluate the plan, actual costs & budget from the R/3 linked objects. All the information are pulled from the ERP system.
P.S: Which evaluation do you use?
Kind regards,
Zhenbo