Hi all,
Please advise me on the hours calculation is correct???
"Actual hours - assigned hours = remaining hours"
or
"Assigned hours - actual hours = remaining hours"
Thank you
Regards,
Seema P.
Request clarification before answering.
Hi Seema,
Remaining hours = task workload - actual hours.
BR
Matthias