on 2020 Oct 21 7:04 AM
Dear Experts ,
I'm trying to transfer the baseline financial plan data created for the master project and I'm getting in the transfer log that transfer ran successfully , meanwhile no data is transferred.
So can you help me what may be the possible reasons or the missing configuration for this ?
Request clarification before answering.
Issue still exisit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please check the SPRO configuration node 'Define Plan Scenarios' in Project Cost and Revenue Planning. For the plan scenario associated with your financial plan, please check which version type is associated with Transfer Strategy. Only that version will be transferred. Check whether baseline version has transfer strategy or current version because generally version type which is transferred is current.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.