on ‎2019 May 14 3:51 PM
Hi, I am using our New S/4 system - Package 1709.
Committed Date is appearing incorrect inside Planned orders. The committed date in the Planned orders are appearing incorrectly as requirements date. It was supposed to be Component Availability date before S4 HANA upgrade.
From my understanding all the ATP check and the components being allocated or confirmed in order still the dates are similar.
Logic to get the Committed date was: Current date + PDT + GR processing time before HANA, as there is no supply there.
Request clarification before answering.
Hi,
OPPR / OPPQ both are same I believe right ? Please confirm.
So on OPPQ the section on Maintain environment - Checking rule: Is maintained as BO do you want this to be changed to PP checking rule ?
Checking Rule PP in OPPR for material group assign to these products - I dont find anything with section material group...
Thanks,
Deepak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
OPPR is at MRP group which is assigned to MRP1 view / OPPQ at plant level.
If no MRP group is assigned in material master then system read the OPPQ setting.
If MRP MRP group is assigned in material master then system read the check rule from OPPR.
Make sure you have PP for MRP group too.
Best Regards,
R.Brahmankar
Hi,
When I do ATP check in MDVP I get the error: Collective availability check cancelled (Error while resetting).
In my planned order I have N number of components - Out of which just 1 component is missing, but for me all the other components are showing the conf / allocate qty as 0 as well the commited date is same as the requirement date.
OPPR is set with BO - Back order processing for our plant.
OPPQ - Dep reqt availability is with PP for the same plant.
Thanks,
Deepak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It is not getting updated. It shows the same. Not sure why.
Thanks,
Deepak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Did you get any warring message during ATP check for component?
In transaction code MDVP you will get a chance to go to missing parts list immediately after material availability check
Goto transaction OPPR enter plant click "overview".
Checking Rule PP is maintained there.
Also check in OPPQ plant level dependent material availability check Checking Rule PP is maintained
Best Regards,
R.Brahmankar
Hi Brahmankar,
These settings holds good and we did not make any change to ATP or Scope of check etc when we used ECC. Now after the upgrade to S/4 this seems not working. As far we checked all ATP is working fine there in S/4 so there is no issue at all.
But inside the planned orders under component check the fields committed date and conf or allocated qty is not appearing.As they show 0.
Thanks,
Deepak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Scope of check for your checking rule and checking group Check availability replenishment lead time should be used. Please check the setting in OPPJ under determine check it should be with RLT.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.