Change sequence of phases when already released

daniel_humberg
Advisor
Advisor
0 Likes
272

According to my knowledge, the sequence of phases in cpro (4.5) cannot be changed when the phases are already released.

Is this true? For exceptional cases, is there any change to achieve this? Maby via BAPI?

Accepted Solutions (0)

Answers (1)

Answers (1)

mariano_sabiche
Contributor
0 Likes

Hi Daniel;

I have been tested this sequence a lot of times, when project & phases are released are imposible to change.

Only when the phases are "created" can changed.

Error message "DPR_PHASE008".

Hope this help you.

Best regards.

Mariano