Hello,
If i change Calender of a existing project in cProject, will it effect the roles and resource assigned to it and will the budget effect due to this change?
For example- My project duration is from 2012 to 2016, Till date I am using India's calendar for a project in cProject and now i want to use it UK calendar. So, my question is will it effect my budget for past years?
Thanks and regards,
Roshan
Request clarification before answering.
Hi Roshan,
As far as I know, if you have released the project, then manual scheduling & role update according to tasks affects the roles & its demand,subsequently changing the plan costs. If project is not released, then automatic scheduling & role update according tasks changes the role.
Regards,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 3 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.