Which table contains the "change document" data that show in the change document tab in Project Management (for SAP-PPM)?
We are looking for the data for Project and Project Tasks...
Request clarification before answering.
Hi,
I think you can use table CDPOS or FM 'CHANGEDOCUMENT_READ'.