on 2024 Apr 10 2:26 PM
Hello,
In MD04, we have a process order on 27.05.2024 and for this we have exception message 15 and it shows reschedule out to 19.08.2024.
so we are trying to change start date in process order COR2 to 08.08.2024 and system shows "scheduling carried out see log". when we check log we get a message as operation has been scheduled. However, after saving order, date remains same.
I've attached opuz screencapture
MD04
cor2
Please help in finding what we are missing here
Thanks,
MRuchitha
Request clarification before answering.
Check in OMDW the rescheduling horizon in Tcode : OMDW and also the tolerance value forward field value.