Hi All,
In CAT2 transaction, if I manually create a data entry by copying the wbs element from the worklist and save then if I execute the program "DPR_CATS_CPR_TRANSF" the confirmation time is reflected in the Cpro system.
But if I upload data through the zdevelopment (WBS element taken from the worklist ) and run the standard program the confirmation time is not reflected in the Cpro.
Please let me know what to be done to make the confirmation time reflect in Cpro???
The path in Cpro is select any task goto 'Additional Fields' tab you will find Confirmation time in confirmation area.
Thanks & Regards,
Moni.
Request clarification before answering.
hi
have you run the CAT5 transfer transaction