on 2016 Jun 21 7:00 PM
I have all the integration configuration in place between CATS and PPM which are on separate instances. Projects in PPM and PS are Released.
The PS project is not configured for Automatic creation from PPM. It is created Manually and then Object Links to Item+Project and Account Assignment is done later. The FI data is flowing correctly to PPM. But the CATS worklist is not getting filled, neither are the hours posted in CAT2 after the report DPR_CATS_CPR_TRANSF triggering an IDOC to PPM.
Does it matter for CATS Integration to work to have the PS project created automatically from PPM?
Hi,
Did you set up ALE between PPM and CATS system as mentioned in the following SAP Help
http://help.sap.com/scenarios_bus2008/helpdata/en/4b/292153e16b4cb9e10000000a42189b/frameset.htm
Best Regards,
Priyatham
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Priyatham
Yes, I have done those steps.
After CAT2, I see the entries in CATSCO.
After debugging report DPR_CATS_CPR_TRANSF, we could not see anywhere in the program that shows what triggers the IDOC exactly. Do you know any debugging methods/FMs to see where and how the IDOC is not getting triggered?
User | Count |
---|---|
3 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |