on 2021 Dec 15 9:53 AM
Dear community,
I have done the customizing for Attribute Synchronization as follows:
However, when I change basic dates of the WBS elements which are mapped to Decision Points in config. Map Item Type to Project or PS or Commercial Project the dates are not synchronized. I believe I have correctly maintained Object Link Types. What can be the reason for the dates not being in sych.?
Request clarification before answering.
Hi, Judith, thanks for the answer. I checked. All logs are in green. No problems indicated in the log.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can use the following report to check the settings for DFM synchronization first:
Go to customizing: Common Functions > Decision Flow Management Settings > Check and Maintain Settings for DFM.
Use the following parameters (for synchronization from wbs-element to item-DP) to receive the result:
Source Grouping PR
Target Grouping PPODP
Oper./Synch. U
Fill into "Source Field" and "Target Field" and check the result.
Best regards,
Judith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
6 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.