Dear community,

I have done the customizing for Attribute Synchronization as follows:

However, when I change basic dates of the WBS elements which are mapped to Decision Points in config. Map Item Type to Project or PS or Commercial Project the dates are not synchronized. I believe I have correctly maintained Object Link Types. What can be the reason for the dates not being in sych.?

Accepted Solutions (0)

Answers (2)

Answers (2)

egle_silinskiene
Explorer
0 Kudos

Hi, Judith, thanks for the answer. I checked. All logs are in green. No problems indicated in the log.

judith_gabriel
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi,

You can use the following report to check the settings for DFM synchronization first:
Go to customizing: Common Functions > Decision Flow Management Settings > Check and Maintain Settings for DFM.
Use the following parameters (for synchronization from wbs-element to item-DP) to receive the result:
Source Grouping PR
Target Grouping PPODP
Oper./Synch. U
Fill into "Source Field" and "Target Field" and check the result.

Best regards,