Calendar in task is empty

Former Member
0 Kudos
189

Hello,

If i create a new Project from a template, all the tasks use the calender from template. But if i create a new task afterwards, the corresponding field for calender is empty. On other Systems it has "Calender from project" in it.

Main Switch 0009 0009 is set to x and we tryed setting switch 0001 0010 (default calender) to the corresponding calender.

Does anyone know a solution for this issue?

Thank you for the help in advance.

Accepted Solutions (0)

Answers (1)

Answers (1)

francesco_pezzoli
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Markus,

I was unable to replicate the reported system behaviour on our test system, and could no instance of it having been reported by other SAP customers in customer incidents.

I would suggest that you check if there is an implementation of BAdI DPR_ATTRIBUTES which somehow causes this system behaviour (as the BAdI can be used to influence default values on creation, I would think it could have a bearing also on this behaviour).

Besides the BAdI or some equivalent custom logic, I have no other idea what may be causing this behaviour to manifest itself in one system but not others. I would need to look at the behaviour on the affected system in order to identify the root cause. In case the issue persists and you cannot identify the reason, I would therefore suggest that you open a customer incident for me to check.

Best regards