on ‎2017 Apr 20 2:15 AM
Hi,
I am trying to Transfer the budget values from PPM to SAP PS on L1 WBSE which is linked to the PPM item
I have Specified a financial view for budget transfer or planned cost transfer, and have selected the a CO version for this view in Customizing for SAP Portfolio and Project Management
under
Portfolio Management
Global Customizing
Portfolio-Independent Settings
Define Financial and Capacity Views
.
I have mentioned Amount type of Transfer as Budget Transfer and Version as 0.
When pressing the button " Transfer to ERP" a popup appears and when I try to transfer, nothing happens.
I also tried automatic transfer via /RPM/CO_DOWNLOAD. But no result. Blank messages appear in the log
Can someone please help and let me know what I am missing here?
Thanks
AU
Request clarification before answering.
Dear Au,
You can find information under the following Wiki-page:
https://wiki.scn.sap.com/wiki/pages/viewpage.action?pageId=451055506
Best regards,
Judith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
After doing the transfer, run the report
/RPM/FICO_INT_PLANNING.
Maintain the destination system where you have PS/WBS. It can be same as Portfolio Item
Sumati
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.