Automatic scheduling does not activate when confirm Activity Network (PCNF/CNF)

0 Kudos
217

Hi,

The indicator of Schedule automat. is on.

Example for Activity Network:

Constraint finish is 01.05.2022

Actual finish (after confirmation) is 09.01.2022.

Case1: When saving the Network - Schedule finish (E&L) remain 01.05.2022

Case2: When Scheduling the NWA manually (by F9) - Schedule finish is turned to 09.01.2022

Why the system does not trigger the aut.scheduling when saving the Network after confirmation?

TNX & Best Regards

Nir