on 2022 Jan 25 12:05 PM
Hi,
The indicator of Schedule automat. is on.
Example for Activity Network:
Constraint finish is 01.05.2022
Actual finish (after confirmation) is 09.01.2022.
Case1: When saving the Network - Schedule finish (E&L) remain 01.05.2022
Case2: When Scheduling the NWA manually (by F9) - Schedule finish is turned to 09.01.2022
Why the system does not trigger the aut.scheduling when saving the Network after confirmation?
TNX & Best Regards
Nir