on 2008 Oct 01 1:44 PM
Hello,
I am using the automatic hierachical account and there I am missing the button for ad-hoc-calculation on the accouting tag -> costing. I was also saving the project without transfering. But there is nothing that looks like that.
After transfering the project I can see the ECP in the services ...
I have already found the thread: but have no glue how it should work.
Could someone tell me how to enable the link?
Thank you in advance,
Vanessa
Request clarification before answering.
The problem is solved due a correction in the accounting. So the project has been able to be calculated and the button appeared.