on 2022 Mar 07 12:29 PM
Hi Experts,
how do i get Actual dates in sap ppm. i.e (if a phase is closed need to get phase closed date ) and at the project closure need project closure date.
Regards
Gopi.
Request clarification before answering.
Hi Paco
Thanks for the help. Could you please provide table details with dates.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello.
The /S4PPM/TASK table may help you.
With a GUID or EXTERNAL_ID to identify the object, you can filter by object type (OBJECT_TYPE), e.g. PPO=Phase, DPO=Project,...).
You can also filter by status for each GUID/EXTERNAL_ID, e.g. if the object is completed (Completed=40).
With this information you can reach the ACTUALSTART and ACTUALFINISH of each object, corresponding to the dates.
I hope it helps you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Actual dates are only entered on the tasks via confirmation. These actual dates can be used to calculate the scheduled which will roll up to the Phases.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Actual dates are written when you Confirm a Task. There is an app for Confirming Tasks. To get accurate scheduling you need to confirm a task when it is started and in process. Confirm the Start Date and enter a POC or remaining work.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.