on ‎2007 May 22 8:19 AM
Hi,
we are workin on cProject 4.
i have made all settings in spro of cprojects @ accounting, but in evaluation tab, i m nt able to c the values..
what cud be the error ?
i have defined cost/revenue rates and also selected "use rates from cprojects" still not visible in evaluation.
however i can c the rates in resource >> costing tab.
my id <b>amit.dhar@hotmail.com</b>
waitin with points
amit dhar
Request clarification before answering.
Hi,
Please follow the link for Account Integration in Cprojects
<u>
http://help.sap.com/saphelp_cpro31/helpdata/en/home.htm</u>;
Regards
Rehman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have sent a document to your mail id. Let me know if that is useful.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 3 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.