on 2010 Mar 19 12:02 PM
Hello,
I try to adjust the following variant of integration - Multilevel controlling (Structure Element, manual).
I have the following situation:
1. I have the PS Project whith the project structure (project definition and wbs elements)
2. I have the cProject Project with phases and tasks.
3. I have executed step 1 "Assign PS Project" of Account Assignment. (in cProject Project - Accounting -> Account Assignment)
Problem: In step 2 (Assign WBS elements) I did not see PS Structure on the right side of screen.
Dear colleagues in what there can be problem?
Request clarification before answering.
Hi Alex,
Did you check if the PS project is released? This is a pre-requisite.
Matthias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Matthias,
I have checked PS project - status is released. If you were interested by a problem please look the customizings on a following reference - http://files.mail.ru/UM1ZMV
Thank you.
Thanks.
The problem consisted in RFC connection options.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Alex,
I can imagine 2 things: a. check the operative indicators of the WBS elments (planning, account assignment...) b. check the authorizations of the user which logons from cPro to ERP
Regards
Thorsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.