Accounts integration - Multilevel controlling

Former Member
0 Kudos
173

Hello,

I try to adjust the following variant of integration - Multilevel controlling (Structure Element, manual).

I have the following situation:

1. I have the PS Project whith the project structure (project definition and wbs elements)

2. I have the cProject Project with phases and tasks.

3. I have executed step 1 "Assign PS Project" of Account Assignment. (in cProject Project - Accounting -> Account Assignment)

Problem: In step 2 (Assign WBS elements) I did not see PS Structure on the right side of screen.

Dear colleagues in what there can be problem?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Alex,

Did you check if the PS project is released? This is a pre-requisite.

Matthias

Former Member
0 Kudos

Hi Matthias,

I have checked PS project - status is released. If you were interested by a problem please look the customizings on a following reference - http://files.mail.ru/UM1ZMV

Thank you.

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks.

The problem consisted in RFC connection options.

schneidertho
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Alex,

I can imagine 2 things: a. check the operative indicators of the WBS elments (planning, account assignment...) b. check the authorizations of the user which logons from cPro to ERP

Regards

Thorsten