I'm creating a material as HALB in MM01. Now my doubt is
For which materials strategy group should be given ?
Can we give for HALB material or only for FERT material ?
Request clarification before answering.
Hi,
Do you also manufacture the HALB Material, I think we need to maintain Planning Strategy for all the inhouse manufactured materials.
If u have a BOM for HALB Material and you manufacture, we need to have a Planning Strategy for HALB also along with FERT Material.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Praveen
You should define a planning strategy for all those materials where you are planning to create a forecast.
You can define a planning strategy for a HALB material if you will have a forecast at semi-finished product level, with planning strategy 70, for example. Otherwise, if you are only creating a forecast for finished products, it is not necessary to define a strategy for HALBs.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
3 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.