Are you using any EHP version? We have operation wise account assignment in EHP 5 onwards.
In this EHP 5 onwards you need to set configuration activity to get this.
SAP Customizing → Plant Maintenance and Customer Service → Maintenance and Service Processing → Maintenance and Service Orders →Functions and Settings for Order Types → Costs at Operation Level.
If you want in ECC6.0 , you need to look into few tables like
Pass maintenance order number to table AUFK and get AUFK-OBJNR then pass OBJNR to table PMCO with filed WRTTP as "4".i.e "Actual cost" in this table you get plan cost with WRTTP as "1".
I tried with these reports, but it will not show only operation cost. Client want to have ability to get the report like order with operation and operations cost.
thanks,
Vardhan