Dears,

I have 2 group of employees who work from Saturday till Thursday, but one group works on Saturday and the other is off, then the next week they rotate.

So, do I have to create 2 period work schedules in order to assign the first working Saturday to the mentioned group or there is a smarter way that can help me apply this business scenario?

Many Thanks. 

View Entire Topic
corriveau_remi
Active Participant

Periodic Work Schedules have to be ceated and then Generated, and because you need Week 1 and Week 2 altenate for different groups of employees you will need 2 Periodic Work Schedule.

  Weekly Schedule 1 = Sat. Sun. Mon. Tues. Wedn. Thurs.  and Week Schedule 2 = OFF Sun. Mon. Tues. Wedn. Thurs.

Next you will need to create 2 Periodic Work Schedules, both starting on the same date but the one for the "Pair" week starting with Weekly Schedule 1 followed by Weekly Schedule 2, and the second one with Weekly Schedule 2 followed by Weekly Schedule 1.