Dears,
I have 2 group of employees who work from Saturday till Thursday, but one group works on Saturday and the other is off, then the next week they rotate.
So, do I have to create 2 period work schedules in order to assign the first working Saturday to the mentioned group or there is a smarter way that can help me apply this business scenario?
Many Thanks.
Request clarification before answering.
Periodic Work Schedules have to be ceated and then Generated, and because you need Week 1 and Week 2 altenate for different groups of employees you will need 2 Periodic Work Schedule.
Weekly Schedule 1 = Sat. Sun. Mon. Tues. Wedn. Thurs. and Week Schedule 2 = OFF Sun. Mon. Tues. Wedn. Thurs.
Next you will need to create 2 Periodic Work Schedules, both starting on the same date but the one for the "Pair" week starting with Weekly Schedule 1 followed by Weekly Schedule 2, and the second one with Weekly Schedule 2 followed by Weekly Schedule 1.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
7 | |
5 | |
5 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.