on 2020 Jan 15 3:15 PM
Hi All.
We have set am exchange rate type P in the version 0 for our controlling area. The version is set up for plan and actuals.
Exchange type P is updated in the beginnig of the fiscal year with a calculated/supposed exchange rate.
We are using CATS for internal time recording and allocation. The system now uses in default the exchange rate type P within the transfer between CATS and CO. This causes deviation our CO department wants to avoid.
How can I now manage to transfer the internal effort with exchange rate type M instead.
Thank you for any hint.
Best regards and thank you
Soeren.
Request clarification before answering.
Hi Soeren,
Why not to maintain KP26 prices in the Company code currency instead?
It can be NOK, DKK, SEK for example without any currency conversion.
Regards,
Paulo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Soeren,
No, you just need to setup the new planning layout for KP26 where you maintain values in the Company code currency. SAP standard layout is pushing you into CO Area currency, but it does not need to be one. In that case you will be getting translation to CO Area currency and not the other way around.
Regards,
Paulo
Hi,
Check out oss note 691613 - Activity valuation with current exchange rate.
Best regards,
Jonathan Eemans
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 7 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.