on 2019 May 02 10:18 AM
Hi All,
Recently we have changed working hours i.e IT0007 for a set of employees and generation of work schedules is also done. But when we go to pp01 for infotype 1011 ( Create work schedule) still old working hours are shown for Hours per month and hours per year. We want this values to match with IT0007 fields Monthly working hours and Annual working hours i.e new values.
Kindly suggest how to make this work. Thank you
Regards,
Ashok
Request clarification before answering.
Hi,
There could be problem with the validity dates , you have to create another record in PP01 with the dates.. then you can say..
Regards
Sriram