Hi Experts,

I am trying to run a complete Timesheet process for Projects.

I have filled the timesheets via Fiori (My Timesheets v2.0), Approved from CATS_APPR_LITE and transferred using CAT5 to projects successfully. But, I do not see any such timesheet costs posted on same project in CJI3 or S_ALR_87013533.

I checked in COEP table also but no such costs appears there as well.

I have verified all the relevant Customization and Master data but everything looks ok to me.

Also, there is no such Authorization issue.

Attached screenshots.

Kindly suggest.

Best regards,

Sandeep

View Entire Topic
former_member301510
Contributor
0 Kudos

The issue have been resolved.

I changed the Cost accounting variant setting from "Assignment of personnel costs to receiver object" to "Assignment of personnel costs to master cost center" so it worked.