Hi Guys,
We are using SAP EPM 10 SP19
We need to lock the work status for 50 Months ( Time Period ) for various combination dimension
Its possible to lock the Work status through Script Logic Or Input Schedule in the Single shot for All combination
Please suggest
Regards
Dayalan M
Request clarification before answering.
Hi Dayalan,
Are those 50 periods all you have in this Model? If it is then just remove Time from Work Status definition.
If you have more than 50 periods in this Model, do those 50 periods change from one lock to another? If they don't change or change infrequently, create a Node in Time Dimension and set WS on that Node.
Regards,
Gersh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 16 | |
| 8 | |
| 7 | |
| 6 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.