Dear SAP Expert,
On ECC 6.0, My client uses internal order for controlling purchase assets(Capex)
Currently, the S/4Hana Public cloud removes the internal order function.
My client requested to control budgeting for purchase Assets (Capex).
- I use WBS to control the budget, but when I import WBS for budget the system requests input G/L Account.
Can I import directly to WBS?
- The public cloud support "Overall" planning or not.
Please recommendation.
Thanks,
May