on 2023 Feb 07 6:26 AM
Before Blocked BP release 10 Documents are blocked .BP is released SPL block manually .how 10 blocked documents going to release.
Should we release it manually or B2 Job?
Please advise me.
Request clarification before answering.
You can do one of the steps -
1. Retransfer documents as initial transfer
2. Recheck documents in /SAPSLL/MENU_LEGAL - Compliance Management Legal Control Import / Export - Recheck - Recheck Document
System will update new status and ready to use for further processing.