Hi,
We have upgraded our system from 80010INCPMBPC,SAPKW73010 to 80021INCPMBPC,SAPKW73015.
I had refreshed a set of reports before upgrade and recorded run time.
After upgrade took run times for the same reports.
My expectation was improved performance.But some reports taking double time and some reports 50% more time than older version.
Before upgrade reports were refreshed in EPM14 version.After upgrade,refreshed the reports in EPM14 and EPM25.
Both EPM 14 and EPM25 run times are almost similar.
Still we are in performance testing system,not yet deployed in production system.
Anybody faced this kind of situation or anything we are missing?
Best Regards,
Manohar
Request clarification before answering.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 7 | |
| 6 | |
| 4 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.