cancel
Showing results for 
Search instead for 
Did you mean: 

/sapsll/objssf -Delivery entries

jaiji
Explorer
0 Kudos
595

Hi Gts team,

I have scheduled a program sapsll/sdob_objssf_process_r3 in S4 for updating completed status in table /sapsll/CUIT(remove recheck indicator) for deliveries.I have received a message that documents are processed successfully but completed status is not updated in /sapsll/cuit table in Gts.

Please provide your inputs on this.

Thanks

Jaigi

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi Jaigi,

When the blocked document in GTS gets released, an entry is inserted into this table with /SAPSLL/OBJSSF-DOCCM as ‘Blank’ in the feeder system. and when the goods posting is done in ECC, then the CUIT flag is updated back to GTS to make it not relevant for further check.

In your case, it seems the the goods postings are not yet completed and which may be the reason for not seeing CUIT flag update. Can you please check this and confirm?

Thanks,

Pushpraj Mirikar

jaiji
Explorer
0 Kudos

Hi Pushpraj,

Delivery was completed with PGI and updated in /sapsll/Objssf table in S4 system.But when we execute the above program it does not update completed status( Removal of recheck indicator ) in ITREC field of GTS table /SAPSll/CUIT.

Thanks,

Jaigi