Hello All,

While changing the time period getting error "Work status validation failed".

I have configured work status in SAP BPC MS10.0 version. I have done same configuration in DEV and QA system. It's working in QA system but it's not working in DEV system.

I am having time dimension master data from 2007 to 2020. It's working for some time periods and not working some periods.

I am able to change the work status for time period 2007 to 2010 and 2016 to 2020 but I am unable to change the work status for 2011 to 2015.

Could anyone help me how to solve it

Regards,

Mahadev Jundale

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Likes

Have you seen SAP note 1821336? https://launchpad.support.sap.com/#/notes/1821336