Hello,

In our BPC system, we process our Actual data every month where in we load Actual data for the current month and at times the previous months as well to the Actual category in BPC from BW.

Once the Actual load is done, we copy (COPY DMP Package) the same data into two other categories, Forecast1 and Forecast2.

This was the process for the past two years but during this ME activity we started observing that when we copy the data from ACTUAL to the other two versions- the job aborts with the dump TSV_TNEW_PAGE_ALLOC_FAILED.

We had copied the data from ACTUAL to Forecast1 successfully but when we started copying it to Forecast2 it started aborting with the dump. So, we started copying the data from Forecast1 to Forecast2 which gave no issue unlike from ACTUAL.

There is no logic being used; this is just a direct load and we are doing it by month. When we narrow it down to more granular level for copying from ACTUAL, it copies with no issue but when the record count is higher, as in 1.5 M, then it aborts. But, the whole issue is very strange as I said earlier, when we copied from Forecast1 to Forecast2, it gave no errors.

The BW system we are on is SAPK-75005INSAPBW

SAP BPC 10.5 SP11.

Kindly advise. Any suggestions would be appreciated.

Thank you.

Regards,

Leonel S Mario

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member186338
Active Contributor
0 Kudos

"SAPK-75005INSAPBW" - absolutely outdated, upgrade is a must!