on 2022 Jun 22 1:37 PM
Hello All,
This is related to POC based billing for the projects. We are creating project with WBS element. At the percentage of completion of work then we confirm the man hours. After that we create sales order with WBS element, followed by partial billing document for the completed man hours.
We have activated revenue accounting and reporting for the sales document type and item category in RAR configuration. Decision table also maintained for POB with percentage completion as POB type.
Once we transfer sales order and billing to RAR then one POB with two line items created in RAR contract. One item having the billing value but there is no fulfillment percentage. Second item is having 100 % fulfillment with full value again.
As per our standing first item should pick percentage completion from KKA2 - Result analysis calculation but same is not happening.
Kindly suggest if we miss out something in this process ?
Additionally kindly confirm how to transfer percentage completion from KKA2 - Result analysis calculation to RAR ?
Request clarification before answering.
User | Count |
---|---|
10 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.