on ‎2019 Oct 02 12:05 AM
Hello Experts,
I have a question on how to manage environments.
A customer did a lot of changes in BPC Configuration directly in PRD, now we don't know what is in QA transports and what is not. So I was thinking the next:
1. Backup PRD Environment using UJBR.
2. Restore backup in DEV and transport to QA and then to PRD, this to have all enviroments with the same config.
I would like to know if any suggestions or comments about this thinking.
Thanks for you commets.
Best Regards.
Request clarification before answering.
Looks like a correct approach!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vadim,
I hope you're well.
This answer is almost a year old, so just checking that this is still a valid / best approach? My new company is facing the same issue, with environments not in sync, and Production being the only system kept up to date (master data, templates, etc.).
Thanks and best wishes,
Jason
| User | Count |
|---|---|
| 14 | |
| 8 | |
| 7 | |
| 6 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.