Dear PS Experts,

I have a non-statistical project. Some of the WBSs defined under it are statistical and some are not. This is wrong. As you know, I cannot make this change for the current project/wbs.

When I want to create a new WBS in project, the statistical tick is automatically ticked and does not allow me to change it. I want to change it myself.

I wait help!

Accepted Solutions (0)

Answers (3)

Answers (3)

Monisha_Sivaram
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi @controllingprinc34 

When you set the statistical flag for a project, this flag applies to the WBS elements present in the project hierarchy. Upon saving the project for the first time, you cannot change the selection of this flag.

Please refer to the below SAP Help Documentation for the same,
Statistical Project 

Regards,
Monisha.

Thanks for your answer @Monisha_Sivaram. The project is not statistical. Some of the wbs connected to the project are statistical and some are not. I don't want to fix this and never experience it again.
Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

Check your PS configuration for the field status related to the Project Profile you are using.  That is where fields can be set to Display only.

0 Kudos
thank you answer @Ken_Melching .The project type used has not been assigned to the project profile No customization has been done. Could this be the reason?
Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos
The "project type" is mostly for identification purposes and very little control functions. Please check with your SAP configuration expert to analyze your PS set-up.
raymond_giuseppi
Active Contributor
0 Kudos

Start reading KBA 2441384 - Change WBS from statistical to non-statistical (which contains some links of interest)

0 Kudos

thanks your answer. but as i said,When I want to create a new wbs it comes in gray.