Dear PS Experts,
I have a non-statistical project. Some of the WBSs defined under it are statistical and some are not. This is wrong. As you know, I cannot make this change for the current project/wbs.
When I want to create a new WBS in project, the statistical tick is automatically ticked and does not allow me to change it. I want to change it myself.
I wait help!
Request clarification before answering.
When you set the statistical flag for a project, this flag applies to the WBS elements present in the project hierarchy. Upon saving the project for the first time, you cannot change the selection of this flag.
Please refer to the below SAP Help Documentation for the same,
Statistical Project
Regards,
Monisha.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check your PS configuration for the field status related to the Project Profile you are using. That is where fields can be set to Display only.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Start reading KBA 2441384 - Change WBS from statistical to non-statistical (which contains some links of interest)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.