Project Control - Currency

sanne_larsen
Explorer
0 Kudos
142

Hi, 

We're in a implementation project with S4 Public cloud. Our customer is going to use Project Control - enterprise projects for theire investment projects. However we've two question that we don't really understand. 

When creating the project there is a possibility of choosing the project currency, if we don't choose the currency is seems like the system is choosing the company code currency is that correct? 

But, the strange thing we've encounted is that when entering app "Project Brief" it seems like the results in the chart is displayed in the global currency and not the project currency? Can we change this somewhere? Is this how the system should behave? 

Please see example below: 

sanne_larsen_0-1740643292307.png

 


sanne_larsen_2-1740643373133.png

Kind Regards, Sanne

 

 

View Entire Topic
OmarElHajami
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Sanne,

thank you for the request. Yes, when you create an enterprise project, by default, the system will derive the currency from the company code which is derived from the cost center maintained.

Regarding the Project Brief, yes only the global currency is shown and it works as designated.

KR,

Omar

sanne_larsen
Explorer
0 Kudos

Hi Omar,

Thanks for your reply! 

Kind Regards, Sanne